Northern Trail Outfitters is undergoing a Service Cloud implementation and has decided to use the Scrum methodology for the implementation. A business analyst (BA) received an urgent, high-priority change request in the middle of a sprint. Which step should the BA take next?
A. Add the change request to the backlog to be prioritized for the next sprint.
B. De-prioritize some user stories and add the change request to the current sprint.
C. Begin working on the change request as soon as the team has capacity.
Suggest answer: A